Tailings Neutralization Area 376

tailings neutralization

Location

McClean Lake, SK,


Value

$21,000,000


Completed

2016

The scope of work for the new facility includes piping, mechanical, structural, electrical, HVAC, and instrumentation. There are three (3) primary work areas; tailings neutralization, pipe modules between the existing plant and tailing neutralization, and pulp storage and atmosphere leaching. Scope highlights include installation of 5 kilometers of pipe ranging from 1/2" to 10" of multiple materials (copper, CPVC, FRP, HDPE, Carbon, and Stainless). The mechanical scope includes the installation of over 30 pieces of equipment. The electrical scope includes installation of 13.6 kilometers of cable and 55 pieces of equipment.